Decumulation of vakuations

Hi, I am trying to create a module that contains line items for Gross Cumulative Project Valuations. I need to be able to calculate the individual valuation (the current cumulative less previous cumulative) without having time as a dimension. What would be the best way to achieve this in such a module?

Best Answer

  • Currently, there is not a way to cumulate without time as a dimension.

    If you need guidance about how to cumulate in a module with time, let me know!

Answers

  • Development is underway to provide enhanced accumulation functions within Anaplan. These should provide the ability to accumulate on any List (based on the display order of items within the list) and perform a ranked cumulation (based on a ranking Line Item for example).