Level 2 : Sprint 3 : Activity: Build the Product Replenishment Dashboard - AD02

kunal_311
Contributor

Re: Level 2 : Sprint 3 : Activity: Build the Product Replenishment Dashboard - AD02

Hi @einas.ibrahim 

 

I think there is some printing mistake in Course, Even my INV Review screen shows the value as 2099, but when we review the Product Build DB they are the same number for FEB month changes to 2146. which leads to confusion.

I was stuck in this for 4 days, as I used all drill-down method but didn't find anything wrong.

 

Review Screen of "Review the INV01 Line Item Formulas and Summary Method settings"

 

kunal_311_0-1597432455003.png

Review Screen for Product Replenishment DB

kunal_311_1-1597432528069.png