Hi All,
I am trying to import data into my module however, i am not able to map the date format with the modules timescale, the date is in "Week 1 FY19" format and i am not sure which time scale format will be suitable for the same.
Thanks.
Solved! Go to Solution.
If your time format is like "WEEK 1 FY19" then you should keep it as "Match Name" in Import Mapping. Let us know if you are facing any issues with that
Misbah
Hi Sharmagh,
If you navigate to Import settings, you are able to select the format you need either from already excising options OR the custom one, where "?" replace characters which should be ignored - see the screenshot below.
Hope that helps,
Dmitry
If your time format is like "WEEK 1 FY19" then you should keep it as "Match Name" in Import Mapping. Let us know if you are facing any issues with that
Misbah