Hi Nathan, It is a bit more complicated than moving sum due to the calculation being in the future days and time span can be variable, depending on when the factory is open and closed. (Mon could be closed then Tue open then wed closed, Thu open, Fri open) this would make a 5 day lead time not 3. The closure could be all week, then closed for 2 days etc etc. Adrian