Lead Time

Highlighted
Occasional Contributor

Lead Time

Hello,

 

I am trying to calculate production date based on the delivery date and the leadtime.

But the problem that, I need to exclude weekends and it didn't work. I tried several methods but it didn't work on all the cases.

 

Any idea that helps ?

 

Thanks in advance.

 

Regards

2 REPLIES 2
Highlighted
Certified Master Anaplanner

Re: Lead Time

Hello @TAGORTI 

I have an idea, but it might be not fully aligned with best practices.

 

So if you have to calculate lead time only for this current year - you could do it via module which will have a daily timescale with dimension of your material.

So as an input you will have a date order; Lead time (working days).

Please see my small POC:

Screenshot 2020-10-09 at 19.09.07.png

 

Screenshot 2020-10-09 at 19.09.26.png

Regards, Nikolay

Highlighted
Occasional Contributor

Re: Lead Time

Thank you Nikolay.

 

It is a good solution but I don't know if it is recommended as a best practice.

 

Regards