Hi,
I'm trying to find a date that is day 5 or 7 or 16 business days later than Start Date, based on a cell that contains Num Biz Days. I've created a Calendar module where I exclude weekends and holidays I've marked such that I have a Cumulative Working Days where I can Lookup Start date (say it returns 341th working day), add my Num Biz Days, but how could I then return the ending date dimension back? Or another idea that works better with lists.
Thanks!