I am trying to import the countries list (CSV file) into the G2 Country List. When I ran the import this is the result I receive. Anyone who can guide me?
Hi @gulmuneer ,
Whenever the error is "Invalid parent" it means that either parent is missing or invalid parent code so in your case please check your G1 Region list. If that list is not yet populated it will cause that kind of error.
If G1 Region is empty, update that list first before G2 list.
Thanks
Akhtar
@gulmuneer
It's saying your regions are invalid (invalid parent). Take another look at your region list. Make sure it looks like this. If it does, then you'll need to check your mapping which should look like the following:
Thank you. Problem Solved.
Thank you. Problem Solved
Hello community, I have an issue with anaplan report (functionality). The issue I have is within couple of slides. The data in that report is scrolling into a new page. There is a hierarchy in the rows and line items and time in the columns. My problem is, the hierarchy is getting broken in the second page. One of the node…
Hi Community, I’m working with a hierarchical list structure in Anaplan: L1 Region (e.g., Asia, Europe) L2 Country (e.g., India, Pakistan) L3 Local Input (e.g., Mumbai, Lahore, Islamabad) Users are given selective access only at the L3 level (specific cities like Mumbai, Lahore, etc.) so they can input data at those…
As shown in the screenshot, each monthly amount (Jan, Feb, Mar 2024) needs to be paid down in the future months (Jan–Aug 2025). The paydown must satisfy certain conditions specific to each month between Jan and Aug 2025. If the conditions are met, the paydown can occur. For example, if $20 is available to pay in Jan 2025…