Display months as M1, M2 instead of Jan, Feb
Hi! My company uses a 4-4-5 work week calendar. Currently, the system shows the months has Jan, Feb…Dec. but I would like it to display as M1, M2….M12. The reason being is that our M1'23 has a date range of 12/31/22 - 1/27/23, therefore, saying Jan is misleading.
Thanks for the help!
0
Answers
-
Hi @klozano
You need to create a fake time list with "M1, M2, M3 items" and then create a staging module to map “M1, M2, M3” to Anaplan time “Jan, Feb, Mar” etc.
Cheers!
1