I have a client who wants to add a create action to a process. He's not sure that this type of action can be added to a process. If this can be done, can you please provide instructions? Thank you.
@robinsalk if you are referring to the UX create actions below then the answer is No
@robinsalk
Please see this thread
Hi Rob,
Thanks for your workaround. Would it be possible to record a little demo of how to do this?
@robinsalk,
Follow the steps below to create import action to add item into the list which can be added to a Process.
1) Create two lists (New Line Stage (Flat List) and New List (Number List))
2) Create respective system modules:
3) Create saved view:
4) Create the import action and add it to Process:
5) Add the import action the process if required.
Let me know if you've any questions!
Thanks. I appreciate your response. I'm looking for an example of how to do this…' you could "hide" the actions in a different process. For example, do the Create first and then have a "Save" button where it has the Process and actions behind it.' The 'create action' is within the UX
Hello community, I have an issue with anaplan report (functionality). The issue I have is within couple of slides. The data in that report is scrolling into a new page. There is a hierarchy in the rows and line items and time in the columns. My problem is, the hierarchy is getting broken in the second page. One of the node…
As shown in the screenshot, each monthly amount (Jan, Feb, Mar 2024) needs to be paid down in the future months (Jan–Aug 2025). The paydown must satisfy certain conditions specific to each month between Jan and Aug 2025. If the conditions are met, the paydown can occur. For example, if $20 is available to pay in Jan 2025…
I have completed level 2 certificate still I am not confident. I want practice more, where I get small project for practice.