Level 1 Model Building: Employee List won't import Start and End Dates
Hello,
I am on module 1 of the Anaplan training, and when I upload the #E2 Employee List, Anaplan won't pull the start and end dates. I didn't catch that until I got to the creation of SYS08, where #E2 is referenced, but the information won't load to the module, as the start and end dates aren't on the original list. Can you please help?
Tagged:
0
Answers
-
I believe the start/end dates are to be directly imported into the module from the Employees.csv file that is provided, not referenced from elsewhere in the model.0
-
You may also want to reference this solution when importing the employees.csv file to set the format of the dates:
https://community.anaplan.com/t5/Anaplan-Platform-Discussions/Level-1-Model-Building/m-p/51044#M7572