When importing the excel file I keep getting an error message saying “import complete but with failures” and the failure is an invalid code. It says US is not the correct code. Anyone know how to help?
Can you please share a screenshot of the import Mappings? I'm assuming a mapping issue.
In Level 1 Activity 4.6.4 we are Uploading data into the G2 Country list. Please refer these Screenshot. and if you have any question, please let us know.
Hello mgb14, it is strange, I would suggest you » Take a new CSV » Copy the data » Save it with original name » Try reuploading.
Hi @Vitthal & @mgb14 Had a test run with the similar file, haven't faced this issue. Suggest re-build the relevant module and lists from scratch. I see everything is fine from the screenshot which you shared, but yes sometimes system behaves weird. So, try importing again.
Thanks Mate
Hello Community members, Requirement Details: I have 5 levels of composite hierarchy list (A1, A2, A3, A4, A5). I have published a module in UX, Now the requirement is If user select a list member from A4 level in the context selector or Custom Filter I have to display all the list members under that A4 level. How can I…
is there a way to import data with months in columns (usual excel table view)? I have to transform the data so there are rows to cover each period in the upload data form, but I am wondering if there is a better way to just import the data as is with the months in the columns. please let me know what you think. thank you,
Hello, I am receiving an 'Anaplan Upload Failed' Status Description when testing my integration with a Big Query dataset. The integration imports data from BQ to our Anaplan model. No other details given in the error log. I suspect that Cloudworks is not even picking up the file but am not sure what we did wrong on the set…