Switchover merit

Takamasa
Occasional Contributor

Switchover merit

Hi!

I learned that  when Switchover is enabled by selecting a time period from the dropdown list, Anaplan will merge data from the Actual version prior to the Switchover period with data from the Forecast version for the rest of the fiscal year.

So  by changing data from forecast to actual on the forecast version, what is happen as merit of end user? 

2 ACCEPTED SOLUTIONS

Accepted Solutions
Niranth
Contributor

Hi @Takamasa 

 

Switch is generally used in conjunction with Formula Scope, to allow a formula up until the Current Period and allow user input for the periods after current period (Switch over period here should be same as current period). 

image.png

 

image.png

It can also be used, as you observed to combine actual data with the forecast data in the version marked as 'Current' in the model

 

 

View solution in original post

ChrisAHeathcote
Community Boss

@Takamasa 

 

SWITCHOVER is linked to the versions within the model and enables the model builder to allocate actual results to that version.

 

Example - A full year has 12 periods. The current period is Period 3 and the user would like to create a new forecast to reflect changes in the business and the competitive environment. In business change is constant and organisations must make plans to reflect this. When creating this new forecast the model builder can turn on SWITCHOVER and select period 4 as the switchover period. 

 

As the model builder creates the new forecast in this new version values upto period 3 will pull from the ACTUAL version while values from period 4 will SWITCHOVER to the new forecast version.

 

It is used to ensure that the new forecast includes actual data for those periods that have passed as a forecast can no longer be created for these periods as actuals are known.

 

Hope this clarifies.

 

Chris Heathcote

Chris
HeathcoteAndHerran.com

View solution in original post

9 REPLIES 9
Niranth
Contributor

Hi @Takamasa ,

 

I don't think I understood your question. Can you please elaborate what do you mean by 'Merit of End User?' 

Takamasa
Occasional Contributor

Thank you for your reply.

I mean I want to know when you use switchover and use for what.

Niranth
Contributor

Hi @Takamasa 

 

Switch is generally used in conjunction with Formula Scope, to allow a formula up until the Current Period and allow user input for the periods after current period (Switch over period here should be same as current period). 

image.png

 

image.png

It can also be used, as you observed to combine actual data with the forecast data in the version marked as 'Current' in the model

 

 

ChrisAHeathcote
Community Boss

@Takamasa 

 

SWITCHOVER is linked to the versions within the model and enables the model builder to allocate actual results to that version.

 

Example - A full year has 12 periods. The current period is Period 3 and the user would like to create a new forecast to reflect changes in the business and the competitive environment. In business change is constant and organisations must make plans to reflect this. When creating this new forecast the model builder can turn on SWITCHOVER and select period 4 as the switchover period. 

 

As the model builder creates the new forecast in this new version values upto period 3 will pull from the ACTUAL version while values from period 4 will SWITCHOVER to the new forecast version.

 

It is used to ensure that the new forecast includes actual data for those periods that have passed as a forecast can no longer be created for these periods as actuals are known.

 

Hope this clarifies.

 

Chris Heathcote

Chris
HeathcoteAndHerran.com
CommunityMember111277
Frequent Contributor

hi,

 

So do we change the switchover period manually every month manually or will it get changed automatically.

 

Ex - actual period is 3 , switch over period is 4

now, next month, actual period is 4, so the switch over period is 5? do we manually change the period to 5 or will it get changed automatically

michael.chefer
Frequent Contributor

 

@CommunityMember111277 

 

You would need to manually change the switchover every month. 

CommunityMember111277
Frequent Contributor

Thanks!

Takamasa
Occasional Contributor

Thank you so much!

i understand!
einas.ibrahim
Master Anaplanner/Community Boss

Hi @Takamasa 

Just to use accurate language and eliminate confusion...

I would not say "Switch[over] is generally used in conjunction with Formula Scope"

 Formula Scope is a very useful tool in Anaplan but it doesn't require a switchover date to work.

For example,  without the need for a switchover date or in a model that doesn't have a switchover date, I can utilize the  Formula Scope. I can choose that a line item formula would only apply to all versions except Actuals - for example, without the need for switchover date

@ChrisAHeathcote provided a good explanation for the use of the switchover date.


To answer @CommunityMember111277  question ... Yes, a switchover data is something that you need to change periodically (Monthly/quarterly), similar to the Current Date.

Einas