Hi all 

i know we need to change the timescale for DATA03 can anyone guide into how to do this please.

6 REPLIES 6
filip.sypniewski
Master Anaplanner/Community Boss

Re: level2 sprint 2 - Run Process 9 Import Data from the Hub.

Hi @aneeta1,

open your DAT03 module and go to the blueprint. 

From here, you can change Time Scale and Time Range, see screenshot below:

ts.PNG

Let me know if you have additional questions!

aneeta1
Occasional Contributor

Re: level2 sprint 2 - Run Process 9 Import Data from the Hub.

Hi 

for this level2 sprint 2,for DATA03 i made the time range to model calender. is this the right approach 

 

filip.sypniewski
Master Anaplanner/Community Boss

Re: level2 sprint 2 - Run Process 9 Import Data from the Hub.

Hi @aneeta1,

your model calendar starts with Current Year FY20 and you do not have any past years since it is not really needed. This will help to decrease the size of your model. 

In DAT03 you need to import historic Volumes from FY19, therefore your time range should include FY19 and FY20. Otherwise, you will not be able to import your data successfully. 

aneeta1
Occasional Contributor

Re: level2 sprint 2 - Run Process 9 Import Data from the Hub.

HI 

I have attached the screenshot of my blueprint. is the same approach needed to be done for beginning inventory and shipping metrics?

filip.sypniewski
Master Anaplanner/Community Boss

Re: level2 sprint 2 - Run Process 9 Import Data from the Hub.

Great! Your dimensions are correct now.

 

No, it only concerns your Historic Volumes. In Beginning Inventory and Shipping Metric you do not import any historic data. 

aneeta1