Hello Is Delta loads possible for BOMs data in Anaplan and if so what is the best way... Thanks

Answers

  • Hi,
    depends on what you mean by Delta, however here there are some options.

    Option 1 :
    You can create a process which
    1°) copy existing value in another Module / Version to freeze existing value before importing new value (use a Saved View of source module as source for the import)
    2°) import the new value
    3°) Compare

    Option 2 :
    set the value of the import to Update instead of Clear.

    Hope it helps.
    Kind regards.
    Michel.
  • Hi Michel,

    Many thanks for your reply. I will give this a shot.
    Good Day