HI.
Please could you give me some guidance on the below?IF PO Submitted > 0 THEN POST(PO Submitted, Shipping Time Weeks) ELSE 0
@lcapon
For Confirmed PO Delivery there is No Need of IF ELSE Statement, just use the remaining part of your formula which is POST(PO Submitted, Shipping Time Weeks)
Confirmed Purchase Order Request: I see first part of the formula is wrong which checks IF PO Submitted > 0 instead it should be IF Confirmed PO Delivery > 0 THEN use remaining part of your formula.
Also you will have to follow the instructions carefully, you will be asked to use OFFSET first and then later changed to POST - basically explaining it to you the use cases of POST
Misbah
Does this appear correct?
Don't worry - I've amended to use 'Final' Shipping weeks and now appears correct.
Kindly assist me with the below lines. What i need to do first after creating the UX sheet. How to add Product SKU and Time context selectors in the Page. Include the following: Product SKU and Time context selectors. SYS00 Time Settings by Month module, Planning Period Filter for UX saved view (or create a custom view…
Hi, is it possible to use a Network Card in order to show an organizational structure which cannot be managed through Hierarchy Lists, cause there are branches that don't have the same hierarchy levels associated? Example: In a L1 COMPANY > L2 AREA > L3 SERVICE > L4 OFFICE There is a case like this: COMPANY A AREA A…
Hi - I cannot seem to create a migration for Assignment 3 and it will not allow me to update the hierarchy and proceed further. It seems to think that a link has already been created, but I don't see anything. Any ideas?