I made some changes to our development model today and when we came to promote via ALM, the comparison report shows some item that we had not anticipated or expected. The comparison report has a section headed “Data Source Changes”. I made
- one change to the actions to add a new import action
- changed it’s sequence to the top of the actions list and
- added a process called,
I did NOT make any changes to any other data sources. However, the comparison report shows that other data sources have changed. all data sources called “DEV – Model Dated 150424” has been replaced with a simple “-“ Is this because 'Model Dated 150424' has now been archived and the “-“ is just telling the Dev model that these are internal actions?
I need to be 100% sure that I will not break PROD, prior to promotion of the DEV changes.
Thanks