Real to Fake Timescale

I am trying to map the Anaplan monthly timescale to a fake timescale that I have created. 

 

I have a location that has a date MM/DD/YY in which I am wanting to map that to my Month list that consists of Month 1 through Month 60. I am trying to do a formula that will map that date as the Month 1 list item and then each month after that number it Month 2 - Month 60. I have gotten it to map the Month 1 to the actual month, but I am stuck trying to get the months after that to map. Could someone help me?

 

date.JPG

time mapping.JPG

 

 

 

 

Best Answer

  • Hi @dgregs 

     

    Do see if the following works:

     

    1. Create Fake Mth as shown below. I only created 24 members but you can expand to 60 members.

    Screen Shot 2019-12-23 at 18.36.17.png

    2. Cost Center Date Module is created to capture Date of 1st month.

    Screen Shot 2019-12-23 at 18.36.22.png

    3. Another module, i.e. 'Date to Fake Mth' is created. Results are shown in 'Fake Month (List)'.

    Screen Shot 2019-12-23 at 18.36.49.png

    4. Blueprint of 'Date to Fake Mth' module.

    Screen Shot 2019-12-23 at 18.40.14.png

     

    Thanks,

    LipChean