Hi Community. TEXTLIST does not work in Polaris. Planual rule is to avoid using it, however, there are times when the functionality is needed. Has anyone got an alternative or workaround to achieve similar functionality
@TimWard70 you can push the text from the list in to a time dimensioned module then retrieve the result back from the time dimensioned module. See example below, with input to output then underlying calcs
Input:
Output:
Underlying calculations:
Thank you - can see how this would work.
@TimWard70 just learnt that Previous function can actually work outside of the Time dimension on Polaris now. So TextList alternative on Polaris could be further simplified as per below
We are looking for Anaplan end-users to provide feedback on their experiences with the Excel add-in. Interested individuals will respond to this 5-minute survey to help us understand personal needs and behavior when using the add-in. The feedback provided by survey takers is essential to the roadmap of Anaplan's products.…
Estimated Level of Effort:4-8 Hours of Model Building Level of Difficulty: Beginner Recommended Training: L2 Model Builder Training Persona: Casual Model Builder Potential ROI: Decreased planning time Increased accuracy of targets/spreads You Might Also Like: * Historical Snapshotting Top-Down Allocations Whether it's…
Estimated Level of Effort: <4 Hours of Model Building Level of Difficulty: Beginner Recommended Training: L1 Model Builder Training Persona: Casual Model Builder Potential ROI: Decreased response time to address risks Increased forecast accuracy You Might Also Like: * Tops-Down Allocations Historical Snapshotting One of…