CURRENTPERIODEND() does not work
Hi everyone,
I was having trouble when I start learning working on a module with switchover. I set the switchover on and set the month.
It started okay, until I want to get the data from the beginning until the end of the period. I used CURRENTPERIODEND() function. But when I check out the output it turns out empty. I expect that it will shows the end date just before the switchover started.
Did I miss something?
Thanks for your help
Best Answer
-
Hi @deantari
Did you provide the current period in time settings?
if left blank there, you will get blank in currentperiodend() formula.
Thanks,
Manjunath0
Answers
-
You need to have a Current Period set in Calendar for CURRENTPERIODEND1
-
Hi @ManjunathKN
oh no, I left it empty in time setting.
what should I pick as the current period over there?0 -
you need to pick your current planning month.
Thanks,
Manjunath1 -
Hi @MarkWarren
you're right, I left the current period empty as I don't really get it before.Thank you