Hello All, if someone could walk me through the below step by step because I am little bit confused
Hi @omarismailcch1
When you enter blueprint mode of each module there are common elements which you can configure including the "Summary". This is what dictate the aggregation behavior for the dimensions applied to that line item.
The instruction is indicating that you should update the Summary method from None to Any. This means that if ANY month is an actual period, than the quarter & year would also be marked TRUE as these are the summary roll up points.
To complete this activity, within each line item click the ellipse with the summary method column (see yellow highlight below):
You are then able to update the summary method for the line item:
@tifashen888 Thank a lot Tiffany, this is really informative , I did what you told me but the outcome is not the same as what Anaplan example looks like.
this is my blueprint view and final outcome
And this is final outcome form Anaplan
To understand why you may be receiving a different outcome, I'd suggest you familiarize yourself with this function: https://help.anaplan.com/currentperiodstart-a7af7113-e1dc-478d-bbbe-ecb597092991 . It would appear you may have missed a step in defining model calendar.
You need to set the current period first in the module calendar
The function CURRENTPERIODSTART picks the current period from the model calendar itself.
Hi everyone, I'm looking to design a workflow and would appreciate your input or guidance on how to set this up effectively in Anaplan. So, the goal is: Once end users complete their data input, they should be able to trigger a process that: Notifies stakeholders via email with a link to a report. The report includes: A…
I've few actions in our Supply model which when run takes some time on the "generating failure dump" step at the end of the action even though the import is a full success without warning or errors. This is just a few seconds when run for a single action, however we have a process with 120 actions, and most of these…
Hi, My org is looking to explore leveraging Google Apps script to extract data out of Anaplan and update already built templates in Google Sheets. We use the Anaplan Extension currently but find it crashes often with the amount of tabs, data, etc. Has anyone used both Anaplan OAUTH 2.0 API and Goolge Apps Script to write…