Hi All,
Hope you are doing great!
I have to create a peculiar way to calculate weeks and then calculate the days in each of these weeks. Please find below the rules to create a week-
- Weeks will be defined from Sunday to Saturday. The only exception to this rule is stated in rule(4)
- The usual number of days in a week are 7 days in cases where the Start Date and the End Date of the week lie in the same month
- The only exception to rule(2) is in case we move from 1 month to the other while calculating a week.
- From the 1st date of any month, it is mandatory to start a new week irrespective of what day it is.
- The total number of days in a week cannot be less than 5 ever. This rule should never be violated
Let us look at the example below for January 2019 and September 2019 to better understand the way weeks and days in a week are calculated -

| Start Date | End Date | Days in Week |
Week 1 | 01-Sep-2019 (Sun) | 07-Sep-2019 (Sat) | 5 |
Week 2 | 08-Sep-2019 (Sun) | 14-Sep-2019 (Sat) | 7 |
Week 3 | 15-Sep-2019 (Sun) | 21-Sep-2019 (Sat) | 7 |
Week 4 | 22-Sep-2019 (Sun) | 30-Sep-2019 (Mon)(End of the old month - if we don't go till 31st, the next week will have less than 5 days) | 7 |
Week 5 | 01-Oct-2019 (First day of the new month) | 05-Oct-2019 (Sat) | 5 |

| Start Date | End Date | Days in Week |
Week 1 | 01/01/2019 (Tue) | 05/01/2019 (Sat) | 5 |
Week 2 | 06/01/2019 (Sun) | 12/01/2019 (Sat) | 7 |
Week 3 | 13/01/2019 (Sun) | 19/01/2019 (Sat) | 7 |
Week 4 | 20/01/2019 (Sun) | 26/01/2019 (Sat) | 7 |
Week 5 | 27/01/2019 (Sun) | 31/01/2019 (End of the old month) | 5 |
Week 6 | 01/02/2019 (First day of the new month) | 09/01/2019 (2nd Sat as if we take the 1st Saturday, the week would have less than 5 days) | 9 |
What I have done -
I have created user input to input the start date of this week calculation logic.
I have created a list with members like 1.2.3.4.5.6.7……..52 weeks in them
Start Date of [Week 2] will be the End Date[Week 1]+1
Another line item that calculates Start Date + 7 days
If the months of "Start Date" and "Start Date+7" are different that shows we are month end, so I have added additional logic
But then I get a circular Reference with End Date as my End Date formula again involves Start Date
Any support in this regard will be highly appreciated