Creating a New Dashboard by copying from Existing Dashboard

Dear All,

 

I am trying to create a new Dashboard by copying from Existing Dashboard.

My question is do we need to recreate the processes / actions ? (or)

Can we reuse the old actions / processes.

 

P.S: I modified the formula in the New Dashboard view, but the formula changes are reflected in Old Dashboard as well.

 

Regards,

Tharik

Tagged:

Answers

  • Hi Ahamed,

     

    As you have already created the actions/processes, you don't have to create new. You can publish the same on the different dashboards as many times you want. Also, when you do any formula change in the module, it gets reflected in all the views published on different dashboards.

     

    Thanks,

    Anand

    https://in.linkedin.com/in/anand-shekhawat-35645486