Hi,
How would I create a formula that would give me the number of days in a given month?
@neg177
use the Days() function which returns a number
Rob
You can many ways for it. Here is one of them:1. Converting your boolean in number (1 if this day is holiday, 0 if this day is working). Summary Method is SUM.2. Creating LI on Month time scale and input direct equally formula (=Holiday as number). And after this you have LI with holidays count in month.3. You can subtract this LI of LI with DAYS() formula.
Hope this helps.
A couple of things:
Thanks,
How would I exclude Holidays? I have a Boolean Line Item called Holiday that marks if it is a Holiday or not. I was thinking the formula below, but at the seem time doesn't seem correct.
Days()-Holiday?
Thank you
I did not know this platform was subject to Spam, thank you for the heads up and I will look out for so and not reply to Spam. As well I will try to continue to make sure my questions are fully explained so you guys may continue to help me on my Anaplan learning.
Yes, we do have issues where some SPAM gets through our filters, but every day, it is learning and getting better.
With that said, did you get the answer you were looking for or are there outstanding questions that the Community can help you with?
Also it would be great if you can mark your queries as "Solution Accepted" if you feel that your query has been resolved. This would save good amount of time for all.
Misbah
Hi all, The Client ID and Client Secret are available, intended for uploading and downloading files. Could anyone advise how to use these credentials DIRECTLY to make API requests? Thank you!
At Uphold customer support ⭐+1-888-355-2348 accounts may be temporarily disabled or restricted for various reasons. Raise a concern on priority basis at Uphold support ⭐+1-888-355-2348 if you notice any suspected malicious activity, or a problem during account recovery. To contact Uphold support directly at…
I have A6 as the parent list and two sibling lists: A6.5 and A7. The A7 list includes an attribute that maps to A6.5. In the UX, the user will select A6.5 using a content selector, and the grid (dimensioned by A7) should display only the A7 items associated with that selected A6.5. Since the selector is a page context and…