Update Current Period Action from Data Hub Not Working

I’m having trouble with Updating the Current Period action using an imported line item from the Data Hub.

 

I created a systems module and added a Current Period, time formatted line item with no dimensions in the Data Hub and Spoke Model. I created the action to Update the Current Period in the Data Hub and it worked without errors. However, I cannot import the Data Hub line item into the Spoke model. The mappings do not work. I receive an error message that “Current Period” (which is the name of my line item) isn’t recognized in the calendar. If I add a dimension to the modules, the import works but the line item isn’t recognized in the Update Current Period action. Any suggestions please? Thanks!

 

Welcome!

It looks like you're new here. Sign in or register to get started.
Sign In

Best Answer

  • Answer ✓

    Hello @JessicaD 

     

    According an article written by JaredDolich importing data into a dimensionless model is fine for a Data Hub, but model to model imports is very challenging without at least one dimension. 

     

    Create a flat list called “Administration” and add one list item called “Value”. Use this as dimension in your Data Hub module. This will help and allow you to map/ import the current period into the bespoke model.

     

    Let me know if this helps.

     

    Sammy

Answers

  • @saglago 

     

    Thank you - this worked! I was able to create the flat list and apply as a dimension in the Data Hub. In my spoke model, I set up a module with a Current Period, time formatted line item but no other dimensions. I was able to import from the Data Hub. The Update Current Period action recognized the line item since no other dimensions were applied.

     

    I really appreciate your help!

    Jessica

  • I was having the same issue. Thanks for outlining the solution! @saglago 

  • @JessicaD - When I run my Update Current Period Process in my spoke model it takes a minute or two to run. The process is only doing two things (1) updating one line item in a system module from my Data Hub and (2) updating the Current Period. I'm guessing the process time is because of the update to Current Period in Time. Do you experiencing a similar process time? 

  • @saglago I was having the same issue and wondering if there would be a hack for that! Thank you so much!

Welcome!