When ever I try working with the switchover concept in versions..in merging and making the forecast with the actual ...though I get resuls , still my mind pops up with questions about this. Hence I request some one in clearing my doubt please.Tq
@keerthipatiaditya
Switchover is the time period from which the actual version switchesover to the version being displayed.
For example, the forecast version has a switchover date of Jun 21.
When switchover is enabled when the forecast version is selected actual version data will show up to the Apr 21 and from Jun 21 data will switchover to the selected forecast version.
Hope this helps.
Hi,
When Switchover is enabled then the Anaplan will merge Actual data with forecast data.
Here is the example. Considering Switchover date is May
Hope it helps!!
Regards,
Basavaraj Goni
Hi Basavaraj
We are getting actual data in place of forecast data in forecast for switchover of may. But forecast for may is not changing based upon the actual data. Then what is the purpose of switchover when forecast remains the same??
If it is for conversion of forecast data into actual data then, in what scenario we use this switchover functionality?
Please help me in understanding above questions. @ChrisAHeathcote , @JaredDolich
Regards
Yash
@yashbhadoria
Good question. Most likely the line item hasn't been enabled for switchover. Scroll to the right on the line item and you will see a checkbox that turns it on. Another suggestions is to make sure you are using the native versions in your module. TBH, I don't use native versions that often because of the challenges updating the switchover period from outside of Anaplan.
@GONI is right though. It's used to automatically copy actuals into your forecast. For example, Here I have turned on breakback and set it to week 5.
I then enable the line item for breakback and now you can see the first 4 weeks of forecast are no longer editable.
@JaredDolich @ChrisAHeathcote
One quick question about Switchover -
Let say I have selected switchover as May'22 - the below table reflect the correct outcome.
However, let say my forecast value should also change for the remaining months basis on Actuals, then how will I manage that with switchover
Thanks
BB
Great question @CommunityMember111277
I have two possibilities you might consider, one with switchover the other without.
We are looking for Anaplan end-users to provide feedback on their experiences with the Excel add-in. Interested individuals will respond to this 5-minute survey to help us understand personal needs and behavior when using the add-in. The feedback provided by survey takers is essential to the roadmap of Anaplan's products.…
Anaplan Champions! The Community team just posted this announcement that certification badges may not be showing up on your profile probably until next year. Rest assured, you will get credit once you complete and pass the exams. https://community.anaplan.com/t5/Blog/Badges-Back-Soon/ba-p/123385
Users may encounter error and warning messages in PlanIQ. The table below includes descriptions of the messages and details what should be done in order to address them, where applicable. Message types: * Errors will fail the relevant PlanIQ step. Users will have to follow the instructions in order to avoid the errors. *…