How can I pull quarter values (Q1,Q2,Q3,Q4) from Expected Invoice Date ?
The module has no time scale applicable.
NOTE: Time Settings doesn't have quarter totals enabled .
Hi @NancyKhurana
.
1. Even if your model calendar doesn't have quarter total turned on, you can still create a Time Range with 'Quarter' checked.
2. You can select 'Quarter' from the 'Period' formatted line item, and apply the PERIOD() formula.
Thanks,
LipChean
@NancyKhurana
Create a line item for quarter and keep it time formatted- quarter
apply formula period(date line item) . This will give you quarters irrespective of the summary in model calendar
Thanks
Abhay
Hi! I would like to propose the creation of a new Administrator role within Anaplan. Currently, the only way to manage users within a model (outside of the Administration tab) is by assigning the Workspace Administrator (WA) role. However, the WA role requires a Model Builder license, which is significantly more expensive…
Hi everyone, I am trying to create a connection ADO from PostgreSQL, but I consistently receive the following error: Failed to establish a connection The following message was sent from the target system: The SSL certificate is either invalid or not in unencrypted PEM format. Please check your certificate and try again.…
A quick reminder of the Bulk Copy functionality. Bulk Copy allows you copy large volumes of data from one slice of a model to another in a single, optimised operation, instead of using formulas or imports. Use case: copy a version (RF1) into a prior year version (PY RF1) using a versions list to allow for year-on-year…