Hi, I want to run process on 1st Working days in CloudWorks.
If I want to do this, I should use CloudWorks API?
Month
First Working day
4
3
5
1
6
Hi @hyudolee ,
In Clouworks you can set schedule to be run on a fixed date or then for example first monday of the month but unfortunately we don't have option “first working day". I would assume that partly this is because first working day can be different dependant on country.
If you need to get schedule to be run on your first working day of the month your option would be manually updating fixed date in Cloudworks for next month after current month has been run (Maybe set up a calendar reminder to 10th of every month or something like that to remember to do that). Other option would be creating a script that would update fixed date utilising Cloudworks API. Logic for this script could be example to be run everyday to set fixed date to be next first working day of the month.
Best regards,
Pyry
Hello everyone, I hope you're doing well. I'm posting because two of my coworkers are trying to use the Anaplan Excel Add-In Series 4, but they're running into an issue during the connection setup process. When they go to New → New Read-Only Connection (or New Connection) and reach the "Select a Customer" step, no…
Why in my model output is blank, after send explainability data.
I am working on a use case where I need to display the top 5 lines of a module as individual lines, while grouping all remaining lines under an "Others" category. The module is dimensioned by multiple composite hierarchy lists, along with Time and Version. To achieve this, I need to use the RANK function with the Ranking…