I'm not sure if there was a new update that changed the process? I cannot import a date from one model to another. I am trying to import the dates from A01 to A06. I think the checkbox on the mapping page is new. I've tried different variations but can't seem to get it to work.
Thanks in advance
@Olek P
You need to dimensionalize the target with a one member list.
https://help.anaplan.com/update-current-period-action-e94034cd-8004-479f-8c1a-655a296398f0#update-current-period-via-a-data-hub
I have found this:
I will give it a try. Apparently you can't import a list without a dimension, so you have to create a dummy list
https://help.anaplan.com/update-current-period-action-e94034cd-8004-479f-8c1a-655a296398f0#fmw7f0ibjn-schedule-update-current-period-actions-and-processes
A while back, I shared a pattern for extracting and reporting on Anaplan audit data using a Python project hosted on GitHub. I wrote that during my time on the Operational Excellence Group (OEG) at Anaplan. The Python solution still works, and plenty of teams are running it today. The problem it solves hasn't changed:…
We are looking for Anaplan end-users to provide feedback on their experiences with the Excel add-in. Interested individuals will respond to this 5-minute survey to help us understand personal needs and behavior when using the add-in. The feedback provided by survey takers is essential to the roadmap of Anaplan's products.…
Estimated Level of Effort:4-8 Hours of Model Building Level of Difficulty: Beginner Recommended Training: L2 Model Builder Training Persona: Casual Model Builder Potential ROI: Decreased planning time Increased accuracy of targets/spreads You Might Also Like: * Historical Snapshotting Top-Down Allocations Whether it's…