Hi team,
Can you please guide me how to removed the FY- 19 / 20 / 21 from the sheet and doing so will it effect my data.
I want to remove the FY-19/ 20 from this worksheet highlighted in yellow.
Regards
Adarsh
Hi @adarshbarodia
You can do this by applying a filter to the saved view, or by applying a filter in UX if you are using a custom view.
The filter should show only the months (You want the summary for the filter line to be set to NONE) and not the years.
Here is an example if you wanted to show all forecast periods:
Then if you are using a saved view, you can simply apply that time filter, and re-save the view.
If you are using a custom view in UX, then you can apply the filter there.
Once you are in edit mode and click "view designer" within that card:
First, Click filter:
Then apply the filter to the data accordingly. Make sure to hit the "apply" and Update at the bottom.
After either of these options, your graph should be updated accordingly.
Let me know if this is not clear.Jason
@adarshbarodia
That would seem to be a way to do this but @jasonblinn solution is better. Can you create a system module that filters out the aggregate time filters? Just create a module with your model calendar only. Create a boolean line item that equals "TRUE". <--- Bingo! that's your filter. Apply that to your chart and, like magic, the aggregates are gone. Give it another try! You've got this.
I tried to use show/hide option >Time
I choose the specific columns leaving FY 19/20/21
But the data is still visible in the line chart on right
Hi, i have a source that uses a connection to Skutrak, and i selected 3 columns when i created the source, now i want to bring in a 4th column, do i have to recreate a source from scratch and then use that in a new transformation view and do all the work i did again, or can i update the source column selection, and add the…
We have 2 dataspaces (Training and Current), the training one had a link to a list in a Model. When i tried to add a link to the same list in the Current dataspace, the link showed as ticked and i could not select it. Does this mean you cannot link to the same source in 2 different dataspaces? It shows a tick in the LINK…
A quick reminder of the Bulk Copy functionality. Bulk Copy allows you copy large volumes of data from one slice of a model to another in a single, optimised operation, instead of using formulas or imports. Use case: copy a version (RF1) into a prior year version (PY RF1) using a versions list to allow for year-on-year…