Level 1 6.6.5 FY19 checked

Hey,

 

When checking my work versus the example, I see that FY19 is checked for Module 'SYS01 Time Settings' for Forecast Year?

 

Below is the correct solution:

jfreemanallitix_0-1627474758895.png

Here is what I have:

jfreemanallitix_2-1627474869908.png

This is what I have for both modules:

 

jfreemanallitix_3-1627475032379.png

For summary on Forecast Period? I also did 'None' and 'Any'. In both cases, the check on FY19 was checked. I double checked my Time Settings as well:

 

jfreemanallitix_4-1627475153236.png

Any help is appreciated!

Josh

 

 

Comments

  • @jfreemanallitix 

     

    Can you check if you have Current Period set for any month of FY20

     

    Misbah_0-1628066272758.png

    Misbah

  • @jfreemanallitix 

    SYS01 Time Settings.Forecast Periods? and SYS01 Time Settings.Forecast Months Only? are dimensioned by YEAR. 

    Change these to months and the SYS02 Forecast Years? line item will calculate correctly.

     

    Good luck